• Korangi, Industrial Area, Karachi

Projects in 2025

S.No. Client Project Title Agreement No Contractor/Sub-Contractor Year Status
1 K-Electric

Our team successfully rehabilitated the 220kV transmission towers #42-47 CCPP-KCR, ensuring reliable power transmission and safety.

Sub-Contractor 2025 Completed
2 PAEC

Survey, Geotechnical Study, Design, Engineering, Manufacture, Supply, Laying, Construction, Instalaltion, Erection, Testing, Commissioning, Energization And Handing Over On Turnkey Basis A New 132 Kv Double Circuit Transmission Line (Permanent Arrangement) From K-Electric 132 Kv Baldia Grid Station K2-K3 Gantry (On Trunkey

Contractor 2025 Completed
3 NTDC

Procurement of Plant - Design, Manufacture, Supply, Instalaltion, Testing & Commissioning of 500kV Double Circuit Quad Bundle Trasnmission Line from Suki Kinari Hydro Power Station to Interconnection Point of Existing Neelum Jhelum 500kV Double Circuit Quad Bundle Trasnmission Line (approx. 75km), using ACSR "Bunti

Contractor 2025 Completed
4 NTDC/ China Electric Power Equipment and Technology Co Ltd 500kV/ 220kV/ 132 kV Lahore North Substation & Extension Works at 500kV/ 220kV/ 132 kV Nokhar Substation Project (Lot B) + Lot C + Lot D + Lot G + Escalation Lot B & Escalation Lot C + Safety Lot B & Safety Lot C Contractor 2025 Completed
5 Shanghai Electric Civil work and Tower/ Pole erection Stringing FWP01-1 New Port Qasim to KDA transmission Line Contractor 2025 Completed
6 K-Electric Rehabilitation of Tower Foundation and Stub on multiple KE TLs location Contractor 2025 Completed
7 K-Electric Procurement Of Services For The Protection Of EHT Cables Inside Nala For Qayyumabad Region. Contractor 2025 Completed
8 K-Electric MEW Phase 04 Extension Contractor 2025 Completed
9 K-Electric Composit Insulator+ HF 132kV PW-BOC (Services) Contractor 2025 Completed
10 K-Electric Contract for OPGW Services Contractor 2025 Completed
11 Lotte Chemical

To carry out replacement of 220 kV Transmission Line OPGW--

Sub-Contractor 2025 Completed
12 K-Electric KDA-Bal-NKI-Sur Ins Replacement PhaseIII Contractor 2025 Completed
13 K-Electric SERVICES FOR DIV OF 220KV BL KKI 1 &2 Contractor 2025 Completed
14 K-Electric 220kV NPQ- KDA I, II T#82A-83A(UC 1-1) MEW Phase 5 Contractor 2025 Completed
15 K-Electric

REHAB. SERVICES FOR PSM

Contractor 2025 Completed